How to synchronize Dependencies

If the Source object is updated and published, the number of Dependency Synchronization problems will be displayed in the Side panel of the Target object.

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select the project which is the Target of the dependency in the Project Data Selector.

  4. In the Gantt spreadsheet, select the task which is the Target object.

  5. In the Task panel, select the Dependency tab (DependencyBlue).

  6. Click on the SYNC button to synchronize the dependency.