How to create a Task to Task Dependency – Copy Mapping

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select the project which is the Target of the dependency in the Project Data Selector.

  4. Create a new task, so that the data coming from the Source object will be imported in this task.

    How_to___Copy_Mapping.png
    Note

    Creating a Copy mapping dependency directly with the Design task will override the Design task data.

  5. In the Gantt spreadsheet, click on the Cmd (GearGantt) button, and select the Create Dependency command.

  6. In the Create a New Dependency popup, select:

    1. Mapping Type: Copy

    2. Task to Task dependency

    Note

    If a Default Mapping has been selected in the Project Administration dialog box, you can leave the Mapping Type field blank.

  7. Select the Project Source in the list, and then the Task Source.

  8. The Gear (GearGanttDependency) icon indicates that the task has a dependency with another object. This specific Gear icon is only displayed on the Target task.