How to create a Project to Task Dependency – Copy Mapping

  1. Log in to the HTML5 client.

  2. Select the Work workspace, Gantt tab.

  3. Select the project which is the Target of the dependency in the Project Data Selector.

  4. Create a new task, so that the data coming from the Source object will be imported in this task.

    Project_to_task_copy.png
    Note

    Creating a Copy mapping dependency directly with the Security System project will override the Security System project task data.

  5. In the Gantt spreadsheet, click on the Cmd (GearGantt) button, and select the Create Dependency command.

  6. In the Create a New Dependency popup, select:

    1. Mapping Type: Copy

    2. Project to Task dependency

    Note

    If a Default Mapping has been selected in the Project Administration dialog box, you can leave the Mapping Type field blank.

  7. Select the Project Source in the list.

  8. The Gear (GearGanttDependency) icon indicates that the task has a dependency with another object. This specific Gear icon is only displayed on the Target task.