% Critical Chain Complete

The purpose of calculating the percentage of the critical chain completed is to focus attention on problems that jeopardize progress on the critical chain tasks and, thus, impact the target finish.

% Critical Chain Complete = (Sum of the Baseline Duration of the Tasks on Critical Chain - Sum of the Remaining Duration of the Tasks on Critical Chain) / Sum of the Baseline Duration of the Tasks on Critical Chain.

Note

This implies that a baseline MUST be saved before Sciforma can properly compute % Critical Chain Complete values and before users can rely on these values to be valid and meaningful (e.g., when capturing and examining data points for Fever charts).