The Assign Resources dialog box has been designed to identify Resources that are a good fit for the project assignments.
The upper section of the dialog box provides the following information that enables the user to understand the context of the assignment: Project Name, Task Name, Task Start and Finish dates, Duration of the task, and % completion of the task.
The Assignments spreadsheet allows the user to review both current assignments (Already Assigned section) and the ones he/she is about to make (New Assignments section).
For each assignment, the following information is displayed: Resource Name, Rate, Total Effort, and time-distributed Effort.
In addition, the following commands can be displayed:
Remove | Allows the user to remove the assignment from the New Assignments section. | |
Uniform | Indicates that only uniform assignment is allowed. Upon clicking on this icon, the assignment allows non-uniform assignment. | |
Non Uniform | Indicates that non-uniform assignment is allowed. Upon clicking on it, the assignment only allows uniform assignment. | |
Edit | Allows the user to open the Labor Assignment dialog box. This button is only available in the New Assignments section. | |
More | Provides access to the following commands:
|
Upon activating the Show Remaining Usable Effort () display option, an additional row is displayed for each resource, indicating the time-distributed Remaining Usable Effort.
Depending on the context, the list of resources available for selection will display either the resources belonging to the Project Team, or the Resources belonging to the selected Organization.
The following options are available to manage the display of the assignable resources list:
For each resource, the time-distributed Remaining Usable Effort is displayed.
Indicators are provided to highlight the resource's capacity:
Green | The % Used is equal to zero. | |
Amber | The % Used is greater than 0% and less than 100%, meaning the Total Effort is greater than zero but less than the resource’s Available Effort. | |
Red | The % Used is greater than 100%, meaning the resource would be over-allocated if all commitments were to become actual assignments. | |
Grey | The available effort is equal to zero. |
The following commands are available to manage the assignable resources: